Today we started welding the clevises for the rear suspension onto the frame. Four of the clevises have been tacked on already and are awaiting the final weld.
Friday, December 27, 2013
Tuesday, December 17, 2013
Primary frame welding complete
Today we finished welding all the primary parts of the frame. The only remaining things are clevises and other secondary parts that mount to the frame.
Friday, December 13, 2013
Rear engine bracing members machined
Today we machined the two rear engine bracing members and they are now ready to be welded. We are also almost done with welding the entire frame, only a few members remain at this point.