Friday, January 31, 2014
Freshmen Spirit Day
Today we attended the Freshmen Spirit Day event at California State University, Los Angeles. A lot of freshmen showed interest in our vehicle, and we hope to recruit new members to our team!
Thursday, January 30, 2014
Ride heights compared
Today we took the welded frame and put it on blocks to simulate the ride height. We then compared it to previous year's car. The new car is significantly lower than the old car. We plan to adjust our suspensions to increase our ride height, since a low ride height makes us more prone to impacts.
Wednesday, January 29, 2014
A-arms machined
Today we machined out both of the A-arms and the rod end inserts for them. We have also welded the rod end inserts onto the applicable A-arm members. We are now ready to tack weld together the A-arms.
Saturday, January 25, 2014
Rear suspension assembled
Today we finished up the members of the rear suspension and tack welded them together. We have also tack welded on clevises onto the rear of the frame. With clevises on the rear of the frame, we then assembled the rear suspension and tested it out.
Thursday, January 23, 2014
Friday, January 17, 2014
Plasma cutting lessons
Today we had a quick lesson in plasma cutting. For quick rough cuts, this would be an easy way to do them.